Building project notices w/c 10 October

There are medium to high level noisy works planned on site for this coming Saturday morning (8am-1pm) - 8th October.

w/c 10th October

  • FF Criminology - making good and paint to walls
  • FF Main Core - drilling and fixing for 2nd fix electrical and glazed screen installations
  • SF Main Core - drilling and fixing for ceilings, partitions and glazed screen installations
  • SF Toilets - drilling and fixing for ceilings, partitions and mechanical/electrical fixings
  • Main Lift Shaft - drilling and fixing/moving materials for main lift installation

Toilet facilities are available on the GF next to the Lecture Theatre 2 and next to the Cube, and on the First Floor adjacent to the English Graduate Common Room.

Bike racks at the back of the building (near the Manor Road entrance) under the building overhang have been reopened and there are temporary racks on the grass to the front of the building.

The main building reception on the first floor is now open.