Building project updates w/c 19 September

w/c 19th September

  • English Faculty (GF/FF) – Latex to floors
  • English Faculty (GF/FF) – paint and decorations to walls and ceilings
  • English Faculty (GF/FF) – drilling and fixing for external window installation (provisional)
  • Main Core Areas (FF/SF/TF) - drilling and fixing for ceilings and partition installations
  • Criminology (FF) – laying floor finishes
  • BLL Entrance area (SF) - drilling and fixing for second fix electrical items; installation of reception desk
  • DDA Entrance (GF) – paint and decorations to walls and ceilings
  • External Works – laying paving slabs to external path; mini excavator to be used to re-grade soil to external path

Toilet facilities are available on the GF next to the Lecture Theatre 2 and next to the Cube, and on the First Floor adjacent to the English Graduate Common Room.

Bike racks at the back of the building (near the Manor Road entrance) under the building overhang have been reopened.

The porters have relocated to a desk by the Manor Road entrance to the building.