Building project notices w/c 8 February

Reminder: A wireless survey is going to take place on Monday 8 and Tuesday 9 February. The survey will involve erecting a temporary wireless access point and taking measurements of signal strength throughout the building. The surveyors will need access to the whole building but should not be in each area very long.

w/c 8 February

  • SF / FF / GF BLL area plastering to ceilings and walls
  • SF / FF / GF mist coat to walls
  • SF / FF / GF fixing into metal frame for plasterboard studwork
  • GF BLL area drilling into concrete floor for metal plates and roller bases for racking
  • GF North area fixing into concrete for metal frame ceiling
  • BLL lift shaft internal block laying
  • External – bricklaying to book delivery extension
  • GF WCs breaking out concrete for drainage runs – Tuesday and Friday between 1pm to 5pm
  • SF / FF / GF fixing into metal frame for plasterboard studwork
  • SF drilling into concrete for mechanical and electrical works
  • FF BLL - slab cutting – (Wednesday and Thursday only)

Activities which are expected to take place in the following week (w/c 15 Feb) are as follows:

  • SF / FF / GF drilling into concrete for mechanical and electrical works
  • External – bricklaying to book delivery extension
  • SF / FF / GF fixing into metal frame for plasterboard studwork
  • SF / FF / GF plastering to walls and ceilings
  • GF WCs breaking out concrete for drainage runs – Tuesday, Wednesday and Friday between 1pm to 5pm
  • GF area drilling into concrete floor for metal plates and roller bases for racking