Building notices w/c 31st August 2015

  • Tuesday 1st September  – Friday 4th September : Soft strip of all Phase A areas in readiness for demolition which will entail removal of items such as mirrors, cladding, shelves etc
  • Tuesday 1st September – Friday 4th September: Heritage surveys taking place for recording purposes
  • Thursday 3rd September and Friday 4th September:  Demolition of GF toilet area
  • Tuesday 1st September – Friday 4th September :  Completion of site set up including scaffolding